Construction Delays Impact Marshall Intersection Ahead of School Year

Construction site showing machinery and road signs near a school intersection

Marshall, MN, August 29, 2025

News Summary

In Marshall, MN, paving delays at the intersection of West College Drive and Saratoga Street will likely postpone its reopening as a new energy center project progresses. The intersection is closed to vehicles, and with school starting soon, safety measures for student crossings are being implemented. R and G Construction is in communication with local schools to ensure student safety during this transition.

Marshall, MN – Paving delays at the intersection of West College Drive and Saratoga Street are expected to continue as work on a new energy center project progresses. The intersection is currently closed to vehicle traffic, and while utility and grading work is taking place for a new roundabout, it is unlikely to reopen by the start of the school year next week. To facilitate school traffic, plans are in place to create a safe crossing path for children. Classes at surrounding schools, including Southview Elementary and Marshall Middle School, begin on Wednesday.

Representatives from R and G Construction are actively communicating with Marshall Public Schools to keep them abreast of the developments and ensure the safety of students. As children adjust to the changes, a construction representative intends to be present at the intersection to guide them. Marked paths will help children cross safe from traffic, providing a hard surface for additional security.

The concrete paving work at West College Drive and Saratoga Street is a critical component of this construction effort, which has led to the intersection being closed to vehicles since last week. R and G Construction expects to finish integrating the ends of the intersection with the remainder of the street in the next week or two, depending on weather conditions.

Adjacent to the intersection, utility line updates and ongoing grading work are happening near the National Guard Armory. Workers are nearing the end of water and sewer pipe installations, with further reconstruction planned. The Minnesota Department of Transportation is overseeing the construction of a new roundabout at this three-way intersection.

This construction is part of a broader redevelopment effort culminating in a fourth and final phase set to begin this fall. Motorists are advised to seek alternate routes, as detours are now in place on Lyon County Road 7 and Minnesota Highway 23, although some segments of Highway 19 remain open to local traffic.

In addition to these infrastructure upgrades, the Marshall Energy Center project commenced on July 22, with a groundbreaking ceremony held earlier this summer. This initiative is part of the Missouri Public Utility Alliance’s “Building MO Power” program, with the energy center projected to cost $175 million. The facility will feature four natural gas turbines that will go operational in two phases—2026 and 2029. This will generate between 99 to 134 megawatts of power, enough to supply electricity for three cities the size of Marshall.

The aim of the energy center is to bolster grid reliability and maintain affordable energy costs for residents and businesses while contributing to job creation and infrastructure development in the community.

Key Features of the Current Projects

Feature Details
Intersection Construction New roundabout and paving at West College Drive and Saratoga Street
Crossover Safety Safe crossing path for children when school resumes
Utility Upgrades Installation of water and sewer lines, utility relocation ongoing
Traffic Diversions Detours in place around construction zones
Energy Center Project $175 million energy center to enhance electricity reliability, slated for completion in 2029

FAQ

What is the current status of the intersection construction?

The intersection of West College Drive and Saratoga Street is closed to vehicle traffic due to ongoing construction. Paving work is expected to delay reopening until after the start of the school year.

When do classes start at nearby schools?

Classes at Southview Elementary and Marshall Middle School begin on Wednesday.

Are there any safety measures for children crossing the construction zone?

Yes, marked paths for children to cross safely at the intersection are planned.

What is the expected timeline for the new energy center project?

The Marshall Energy Center is anticipated to be operational in phases, starting in 2026 and concluding in 2029.

What additional construction is happening in Marshall?

Utility work, roadway reconstruction, and grading is ongoing near the National Guard Armory and will continue until the completion of the fourth phase of construction.


Deeper Dive: News & Info About This Topic

HERE Resources

Additional Resources

STAFF HERE HOUSTON TX WRITER
Author: STAFF HERE HOUSTON TX WRITER

The HOUSTON STAFF WRITER represents the experienced team at HEREHouston.com, your go-to source for actionable local news and information in Houston, Harris County, and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as Houston Livestock Show and Rodeo, Art Car Parade, and Chevron Houston Marathon. Our coverage extends to key organizations like the Greater Houston Partnership and Houston Area Urban League, plus leading businesses in energy and healthcare that power the local economy such as ExxonMobil, Schlumberger, and Houston Methodist. As part of the broader HERE network, including HEREAustinTX.com, HERECollegeStation.com, HEREDallas.com, and HERESanAntonio.com, we provide comprehensive, credible insights into Texas's dynamic landscape.

ADD MORE INFORMATION OR CONTRIBUTE TO OUR ARTICLE CLICK HERE!
Advertising Opportunity:

Stay Connected

More Updates

Exterior view of Prosperity Bank building in Houston

Prosperity Bank Announces Dividend Payment

Houston, January 22, 2026 Prosperity Bancshares, Inc. has declared a dividend payment of $0.60 per common share, scheduled for April 1, benefiting shareholders and reflecting financial

Would You Like To Add Your Business?

Sign Up Now and get your local business listed!